FCC draft would make 400-foot coverage optional in AURA's 450 MHz drone license
The Federal Communications Commission was set to vote on November 19 at 10:30 a.m. Eastern on a draft that would allow AURA Network Systems to turn its 450 MHz licenses, currently tied to individual sites, into a single nationwide license. The licenses cover drone control links and general aviation, DroneXL reported. The company would receive the license without an auction and without a windfall payment.
The draft and its altitude benchmarks
AURA holds licenses at 54 sites. Chairman Brendan Carr posted the draft online on October 29, the same day the agency made 800 MHz Cellular spectrum available to drones. DroneXL noted that a proposal from January 2025 would have obliged AURA, if it retained its high-altitude service, to reach 400 feet across 35% of every regional license area in the FCC's system within eight years. The new draft keeps the nationwide license and the high-altitude service but drops that 400-foot requirement.
Under the draft, AURA could meet its build-out with 25,000-foot service over the lower 48 states, Hawaii and part of Alaska, plus 5,000-foot coverage over half of the lower 48 and Hawaii within four years and 90% within eight. Coverage at 400 feet, which DroneXL described as the Part 107 ceiling, becomes optional. The 5,000-foot metric appears in the draft “as requested by AURA.”
The 400-foot alternative would instead require 35% coverage of the lower 48 and Hawaii at four years, rising to 70% at eight, plus 9% of Alaska at four years and 19% at eight. The construction notice is the point at which AURA selects its option, and later licensees would receive an identical selection right. DroneXL noted that the territories get no targets.
In its comments, AURA said its network can provide low-altitude coverage but expects demand mainly in controlled airspace between 3,000 and 10,000 feet. It called the low-altitude benchmark unnecessary and said a 400-foot alternative “could ensure that the rules are sufficiently flexible” for future uses. The draft is also internally inconsistent: paragraph 63 sets the final 400-foot target for Alaska at 19%, while footnote 174 gives 21%.
Engineering, eligibility and penalties
The draft accepts AURA's engineering argument. The band is 650 kilohertz wide, and the FCC wrote in paragraph 61 that a network serving both high-altitude and 400-foot flights is “most likely not feasible.” The Enterprise Wireless Alliance made the same point, and the draft says AURA was the only commenter to propose specific numbers.
The First Person View Freedom Coalition asked the FCC to write “below 400 feet” instead of “at 400 feet.” The draft declined, citing the FAA's wording. It also dropped region-by-region measurement after AURA argued that building out regions without demand “would result in significant wasted investment.”
Penalties are severe. Missing an interim metric shortens the term from 15 years to 13 and moves the final deadline to year six. Failing a final metric ends the license automatically. Coverage counts only if AURA's links meet the RTCA DO-406 standard or a later standard the FCC adopts.
DroneXL reports that the draft sees no undue enrichment for AURA and does not require a windfall payment or a holding period. The order, citing AURA's comments, puts AURA's spending on the band at $100 million since its 2021 waiver. According to the draft, a windfall payment would probably be so small that it sits under a de minimis threshold, a legal term for a trivially small amount.
According to DroneXL, the eligibility test appears designed for a single company. To qualify, an incumbent would need 25,000-foot service across the lower 48, Alaska and Hawaii on all available channels, operating from sites that prevent others from building regional service. In its filing, AURA argued that the criteria confirm the applicant “is in fact the only entity that can operate in the band.” The First Person View Freedom Coalition opposed a nationwide license for a private company, warning of underinvestment and monopoly pricing. The draft replies that AURA has long been the sole licensee and that “neither of these consequences is apparent in the record.”
Radar and prison jamming rules
The draft's 24 GHz section would add secondary radiolocation between 24.45 and 24.65 GHz, a rule Echodyne first petitioned for in 2018. It licenses each radar by site, however, and rejects Echodyne's requests for geographic licensing and for airborne radars. Temporary-location licenses would cover radars on trailers and vehicles, while radars operating in motion remain barred.
Echodyne had argued that fixed-site rules would be too inflexible for state agencies that relocate radars to answer drone incursions. The FCC said temporary-location licenses cover those cases. On density, the agency sided with the radar makers and rejected a limit of four units per square kilometer that the National Telecommunications and Information Administration had suggested.
On prisons, the draft would permit contraband phones inside correctional facilities to be jammed by non-federal parties, but it does not cover Part 15 unlicensed devices, “under which the majority of UAS control links operate.” Drones over prisons would instead fall under the SAFER SKIES Act of December 2025. Dedrone wanted drones below 400 feet over a prison footprint treated as contraband, but the draft points instead to counter-drone authority for state and local agencies.
The further notice would let licensed jamming systems block unlicensed signals at 2.4 GHz, 5 GHz and 6 GHz in parts of facilities where such devices are banned. DroneXL noted those bands serve most consumer drone control and video links, and that the draft frames the proposal around Wi-Fi and Bluetooth devices. The Correctional Leaders Association has asked the FCC to renew its authority before it expires on December 29, 2026.
What DroneXL argues
DroneXL reporter Haye Kesteloo wrote that the draft matches the outlet's October 28 warning: lower 400-foot targets would give one company a nationwide license while making the drone portion optional. He wrote that the draft cites no commenter who disputed AURA's physics. He called a network for larger uncrewed aircraft and crewed planes in controlled airspace useful, but said nothing in the draft requires it to serve the Part 107 fleet at 400 feet, and that the “drone dominance” branding oversells it.